Bulldog Power II (30INR0073) is listed in the ERCOT interconnection queue as a 311 MW gas project in Brazoria County, TX. The filing names TNMP FM524 Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 30, 2030. It records the screening study as complete on February 4, 2026.

Queue ID30INR0073
Project nameBulldog Power II
Status (as published)SS Completed, FIS Started, No IA
SubstationTNMP FM524 Substation
Point of interconnection39703 TNMP FM524 Substation 138kV
CountyBrazoria
StateTX
Voltage138 kV
Capacity311 MW
Resource (as published)GAS/GT
Resource categoryGas (normalized for filtering)
Target commercial operation2030-09-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

TNMP FM524 Substation substation: 2 requests in the ERCOT queue, 2 active totaling 622 MW.

Queue IDProjectMWResourceStatus
27INR0095Bulldog Power311GasSS Completed, FIS Completed, No IA

Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBulldog Power II LLC
CDR reporting zoneCOASTAL
Fuel codeGAS
Technology codeGT
Screening study complete2026-02-04

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first