Elm Flats Solar SLF
ERCOT queue ID 26INR0130
Elm Flats Solar SLF (26INR0130) is listed in the ERCOT interconnection queue as a 125.8 MW solar project in Navarro County, TX. The filing names Tap BRIAR_CRK_8 – POWELL1_8 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of November 1, 2027. It records the screening study as complete on September 1, 2023 and the interconnection agreement as signed on November 21, 2025.
| Queue ID | 26INR0130 |
|---|---|
| Project name | Elm Flats Solar SLF |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap BRIAR_CRK_8 – POWELL1_8 |
| Point of interconnection | Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8 |
| County | Navarro |
| State | TX |
| Voltage | 138 kV |
| Capacity | 125.8 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-11-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap BRIAR_CRK_8 – POWELL1_8 substation: 2 requests in the ERCOT queue, 2 active totaling 125.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 26INR0131 | Elm Flats Storage SLF | 0 | Battery | SS Completed, FIS Started, IA |
Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Orca Falls Solar, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2025-11-21 |
| Screening study complete | 2023-09-01 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.