tap both FarmersVl - Moses ckts substation interconnection queue
3 active projects totalling 800 MW in the ERCOT queue.
3active projects
800active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 22INR0202 | Delilah Solar 1 | 345 | 300 | Solar | SS Completed, FIS Completed, IA |
| 21INR0221 | Samson Solar 1 | 345 | 250 | Solar | SS Completed, FIS Completed, IA |
| 21INR0491 | Samson Solar 3 | 345 | 250 | Solar | SS Completed, FIS Completed, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.