Tap Bois Pump () - Brookston () substation interconnection queue
2 active projects totalling 218.8 MW in the ERCOT queue.
2active projects
218.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0470 | Roxton Solar | 138 | 116.8 | Solar | SS Completed, FIS Completed, No IA |
| 26INR0469 | Roxton Storage | 138 | 102 | Battery | SS Completed, FIS Completed, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.