Tap Bois Pump () - Brookston () substation interconnection queue

2 active projects totalling 218.8 MW in the ERCOT queue.

2active projects
218.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0470 Roxton Solar 138 116.8 Solar SS Completed, FIS Completed, IA
26INR0469 Roxton Storage 138 102 Battery SS Completed, FIS Completed, IA