Tap Valley South – Paris Switch substation interconnection queue

2 active projects totalling 182.2 MW in the ERCOT queue.

2active projects
182.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
22INR0314 Lan Solar SLF 345 182.2 Solar SS Completed, FIS Started, No IA
24INR0262 Lan Battery SLF 345 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.