ERCOT queue ID 22INR0202

Delilah Solar 1 (22INR0202) is listed in the ERCOT interconnection queue as a 300 MW solar project in Lamar County, TX. The filing names tap both FarmersVl - Moses ckts as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2026. It records the screening study as complete on January 3, 2019, the full interconnection study as approved on June 9, 2020 and the interconnection agreement as signed on December 22, 2020.

Queue ID22INR0202
Project nameDelilah Solar 1
Status (as published)SS Completed, FIS Completed, IA
Substationtap both FarmersVl - Moses ckts
Point of interconnectiontap both 345kV 1685 FarmersVl - 1695 Moses ckts
CountyLamar
StateTX
Voltage345 kV
Capacity300 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2026-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

tap both FarmersVl - Moses ckts substation: 3 requests in the ERCOT queue, 3 active totaling 800 MW.

Queue IDProjectMWResourceStatus
21INR0221Samson Solar 1250SolarSS Completed, FIS Completed, IA
21INR0491Samson Solar 3250SolarSS Completed, FIS Completed, IA

Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityDelilah Solar Energy LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2020-12-22
Screening study complete2019-01-03
Full interconnection study approved2020-06-09
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first