Samson Solar 1

ERCOT queue ID 21INR0221

Queue ID21INR0221
Project nameSamson Solar 1
Status (as published)SS Completed, FIS Completed, IA
Substationtap both FarmersVl - Moses ckts
Point of interconnectiontap both 345kV 1685 FarmersVl - 1695 Moses ckts
CountyLamar
StateTX
Voltage345 kV
Capacity250 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2026-09-30
Source datasetlarge

Additional filed fields

Interconnecting EntitySamson Solar Energy LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Ia Signed44069
Screening Study Complete43469
Fis Approved43991
Air PermitNot Required
Water AvailabilityNot Required