Substation Scout

TTRSW substation interconnection queue

2 active projects totaling 520.6 MW in the ERCOT queue.

2 ERCOT queue filings name TTRSW as the point of interconnection, all in Lamar County, TX.

Target commercial operation date as filed: Dec 2026 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Delilah Solar Energy II LLC (1 filing), Samson Solar Energy II LLC (1 filing).

2active projects
520.6active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
22INR0203 Delilah Solar 2 345 317.6 Solar SS Completed, FIS Completed, IA Dec 2026
21INR0490 Samson Solar 2 345 203 Solar SS Completed, FIS Completed, IA Dec 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Lamar County, TX

All 28 ERCOT queue filings in Lamar County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first