TTRSW substation interconnection queue
2 active projects totaling 520.6 MW in the ERCOT queue.
2 ERCOT queue filings name TTRSW as the point of interconnection, all in Lamar County, TX.
Target commercial operation date as filed: Dec 2026 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Delilah Solar Energy II LLC (1 filing), Samson Solar Energy II LLC (1 filing).
2active projects
520.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 22INR0203 | Delilah Solar 2 | 345 | 317.6 | Solar | SS Completed, FIS Completed, IA | Dec 2026 |
| 21INR0490 | Samson Solar 2 | 345 | 203 | Solar | SS Completed, FIS Completed, IA | Dec 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Lamar County, TX
- tap both FarmersVl - Moses ckts: 3 active, 800 MW of 3 filed
- Tap PARIS_SW1_5 -- WOODARD_5: 2 active, 320.8 MW of 2 filed
- Tap Toco Switch (#) – Paris Switch (#): 2 active, 223.1 MW of 2 filed
- Tap Bois Pump - Brookston: 2 active, 218.8 MW of 2 filed
- Tap Valley South – Paris Switch: 2 active, 182.2 MW of 2 filed