Tap Toco Switch (#) – Paris Switch (#) substation interconnection queue
2 active projects totaling 223.1 MW in the ERCOT queue.
2 ERCOT queue filings name Tap Toco Switch (#) – Paris Switch (#) as the point of interconnection, all in Lamar County, TX.
Target commercial operation date as filed: Oct 2026 (2 filings).
Interconnecting entity as filed: MRG GOODY SOLAR PROJECT, LLC (1 filing), MRG Goody Solar Project LLC (1 filing).
2active projects
223.1active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 23INR0225 | MRG GOODY SOLAR | 138 | 170.8 | Solar | SS Completed, FIS Completed, IA | Oct 2026 |
| 24INR0305 | MRG Goody Storage | 138 | 52.3 | Battery | SS Completed, FIS Completed, IA | Oct 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Lamar County, TX
- tap both FarmersVl - Moses ckts: 3 active, 800 MW of 3 filed
- TTRSW: 2 active, 520.6 MW of 2 filed
- Tap PARIS_SW1_5 -- WOODARD_5: 2 active, 320.8 MW of 2 filed
- Tap Bois Pump - Brookston: 2 active, 218.8 MW of 2 filed
- Tap Valley South – Paris Switch: 2 active, 182.2 MW of 2 filed
Site Scanner