TEXAS GULF SULPHUR REPOWER
ERCOT queue ID 24INR0605
TEXAS GULF SULPHUR REPOWER (24INR0605) is listed in the ERCOT interconnection queue as a 16.1 MW gas project in Wharton County, TX. The filing names Gulftie as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of March 27, 2025. It records the screening study as complete on October 27, 2023, the full interconnection study as approved on February 1, 2024 and the interconnection agreement as signed on March 1, 2022.
| Queue ID | 24INR0605 |
|---|---|
| Project name | TEXAS GULF SULPHUR REPOWER |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Gulftie |
| Point of interconnection | 43340 Gulftie 138 kV |
| County | Wharton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 16.1 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2025-03-27 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Gulftie substation: 2 requests in the ERCOT queue, 2 active totaling 416.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 24INR0576 | Boling Generation (TEF-Due Diligience) | 400 | Gas | SS Completed, FIS Completed, No IA |
Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Wharton County Generation, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | GAS |
| Technology code | GT |
| Interconnection agreement signed | 2022-03-01 |
| Screening study complete | 2023-10-27 |
| Full interconnection study approved | 2024-02-01 |
| Air permit | 2025-06-03 |
| Water availability | 2024-01-30 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.