Boling Generation (TEF-Due Diligience)

ERCOT queue ID 24INR0576

Queue ID24INR0576
Project nameBoling Generation (TEF-Due Diligience)
Status (as published)SS Completed, FIS Completed, No IA
SubstationGulftie
Point of interconnection43340 Gulftie 138kV
CountyWharton
StateTX
Voltage138 kV
Capacity400 MW
Resource (as published)GAS/GT
Resource categoryGas (normalised for filtering)
Target commercial operation2028-12-16
Source datasetlarge

Additional filed fields

Interconnecting EntityBoling Generation
Cdr ZoneSOUTH
Fuel CodeGAS
Technology CodeGT
Screening Study Complete45352
Fis Approved45889