Substation Scout

Deaf Smith, TX interconnection queue

11 active projects totalling 6,594.3 MW in the ERCOT queue.

11active projects
6,594.3active MW
11total filed
Queue IDProjectkVMWResourceStatus
29INR0361 Aurelius 3 Natural Gas 345 1,275 Gas SS Started, FIS Started, No IA
29INR0003 Aurelius Solar 345 1,124.2 Solar SS Completed, FIS Completed, IA
29INR0012 Aurelius 3 Wind 345 705 Wind SS Completed, FIS Started, No IA
29INR0004 Aurelius Wind 345 621.6 Wind SS Completed, FIS Completed, IA
29INR0010 Aurelius 2 Wind 345 621.6 Wind SS Completed, FIS Started, No IA
20INR0255 Renegade Project 345 515.7 Solar SS Completed, FIS Started, IA
29INR0009 Aurelius 2 Solar 345 445.4 Solar SS Completed, FIS Started, IA
29INR0011 Aurelius 3 Solar 345 445.4 Solar SS Completed, FIS Started, No IA
23INR0056 Caliche Mound Solar 345 406.6 Solar SS Completed, FIS Started, IA
24INR0200 White Tail Solar 345 226.8 Solar SS Completed, FIS Started, No IA
24INR0134 BRP Hemera BESS 345 207 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.