White Tail Solar

ERCOT queue ID 24INR0200

Queue ID24INR0200
Project nameWhite Tail Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Windmill () – AJ Swope ()
Point of interconnectionTap 345kV Windmill (23910) – AJ Swope (23906)
CountyDeaf Smith
StateTX
Voltage345 kV
Capacity226.8 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-09-21
Source datasetlarge

Additional filed fields

Interconnecting EntityMule Deer Solar LLC
Cdr ZonePANHANDLE
Fuel CodeSOL
Technology CodePV
Screening Study Complete44688
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.