White Tail Solar (24INR0200) is listed in the ERCOT interconnection queue as a 226.8 MW solar project in Deaf Smith County, TX. The filing names Tap Windmill – AJ Swope as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 29, 2028. It records the screening study as complete on May 7, 2022.

Queue ID24INR0200
Project nameWhite Tail Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Windmill – AJ Swope
Point of interconnectionTap 345kV Windmill (23910) – AJ Swope (23906)
CountyDeaf Smith
StateTX
Voltage345 kV
Capacity226.8 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-29
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Deaf Smith, TX: 11 requests in the ERCOT queue, 11 active totaling 6,391.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMule Deer Solar LLC
CDR reporting zonePANHANDLE
Fuel codeSOL
Technology codePV
Screening study complete2022-05-07
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first