Substation Scout

Wautoma Substation substation interconnection queue

2 active projects totalling 970 MW in the BPA queue, plus 1 with terminal status (shown greyed).

2active projects
970active MW
3total filed
Queue IDProjectkVMWResourceStatus
G0670 Not reported n/r 500 Solar STUDY
G0684 Not reported 500 470 Solar STUDY COMPLETED
G0252 Not reported 500 350 Wind WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.