Erie West
Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 8, 2025.
PJM interconnection queue
A PJM queue substation page has the same name: Erie West (PA) — 7 queue requests filed, 1 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Erie South Substation PN-2020-005 and PN-2023-018 |
Not printed | Not printed | Not printed | Not printed | 2024-10-08 TEAC |
| Perry – Ashtabula – Erie West 345 kV Line PN-2023-029 · s3702.1 |
Not printed | $52.4 M | 5/31/2027 | Not printed | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$38.7M → $52.4 M | 2025-08-05 | 2025-08-05 |
| Substations named | ASHTABULA; ERIE WEST → ASHTABULA; ERIE WEST; PERRY | 2025-10-08 | Not reported |
| Substations named | ASHTABULA; ERIE WEST; PERRY → ASHTABULA; ERIE WEST | 2025-08-05 | 2025-10-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2025 RTEP p. 6 |
Perry – Ashtabula – Erie West 345 kV Line | “At Erie West:
▪ Replace disconnectswitches.” 345 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2024 RTEP p. 38 |
Erie South Substation | “At Erie West, replace relaying & line trap” 345 kV |
| 2025-10-08 | TEAC Informational Only - Penelec Local Plan Submission of the Supplemental Projects for 2025 p. 8 |
Perry – Ashtabula – Erie West 345 kV Line | “At Erie West: § Replace disconnect switches.” |
| 2025-08-05 | TEAC Item 06 - Penelec Supplemental Projects p. 3 |
Perry – Ashtabula – Erie West 345 kV Line | “At Erie West:
§ Replace disconnect switches.” 345 kV |
| 2024-10-08 | TEAC Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 35 |
Erie South Substation | “At Erie West, replace relaying & line trap” 345 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.