Substation Scout

French Road No. 2

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Not stateddescribed as
PENELECzone
115 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Erie South Substation
PN-2020-005 and PN-2023-018
Not printed Not printed Not printed Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
Penelec local plan submission for 2024 RTEP p. 37
Erie South Substation No role wording
115 kV
2024-10-08 TEAC
Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 37
Erie South Substation No role wording
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this