Hosensack

Named in 1 PJM planning document for 1 project, on October 6, 2026.

Existingdescribed as
METEDzone
230 kVkV as printed
1mentions

Also printed as: Hosensack Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hosensack Substation
ME-2024-006
Conceptual $39.36 M 12/31/2030 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 09 - MetEd Supplemental Projects - Presentation p. 4
Hosensack Substation “Expand the Hosensack 230 kV bus into a double-breaker double-bus configuration. At Hosensack Substation: Replace two existing 230 kV circuit breakers”
230 kV