Substation Scout

Gardners

Named in 5 PJM planning documents for 3 projects, from August 14, 2025 to October 6, 2026.

Existingdescribed as
METEDzone
115 kVkV as printed
8mentions

Also printed as: Gardners Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mountain Substation
ME-2023-017 · s3605.1, s3605.2
Not printed $11.4M 12/31/2026 31.8 MW 2025-10-08
TEAC
Round Top Substation
ME-2023-020 · s3733.1
Not printed $22.1M 6/2/2028 18.8 MW 2026-10-06
TEAC
Carlisle Pike – Gardners 115 kV 976 Line
ME-2024-008 · s3743.1
Not printed $32.35M 12/21/2029 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ALLEN; CLY; DILLSBURG; GARDNERS; NEWBERRY; ROUND TOP; ROUNDTOP → ALLEN; CLY; GARDNERS; ROUND TOP; ROUNDTOP 2025-08-14 2026-10-06
Substations named CARLISLE PIKE; GARDNERS → GARDNERS 2026-10-06 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 3
Round Top Substation “Revise relay settings at Gardners, Cly, and Allen substations.”
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 7
Carlisle Pike – Gardners 115 kV 976 Line “At Gardners Substation, replace circuit breaker, disconnect switches, and wave trap”
2026-10-06 TEAC
Informational Only - MetEd Local Plan Submission of Supplemental Projects for 2026 p. 3
Round Top Substation “Revise relay settings at Gardners, Cly, and Allen substations”
2026-10-06 TEAC
Informational Only - MetEd Local Plan Submission of Supplemental Projects for 2026 p. 7
Carlisle Pike – Gardners 115 kV 976 Line “At Gardners Substation, replace circuit breaker, disconnect switches, and wave trap”
2026-09-08* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2025 RTEP p. 8
Mountain Substation No role wording
115 kV
2025-10-08 TEAC
Informational Only - MetEd Local Plan Submission of the Supplemental Projects for 2025 p. 8
Mountain Substation No role wording
115 kV
2025-08-14 SRRTEP Mid-Atlantic
Item 05 - MetEd Supplemental Projects p. 6
Round Top Substation “Revise relay settings at Gardners, Cly, and Allen substations.”
2025-08-14 SRRTEP Mid-Atlantic
Item 05 - MetEd Supplemental Projects p. 8
Carlisle Pike – Gardners 115 kV 976 Line “At Gardners Substation, replace circuit breaker, disconnect switches, and wave trap”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this