Mountain

Named in 2 PJM planning documents for 1 project, on October 8, 2025.

Existingdescribed as
METEDzone
115 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mountain Substation
ME-2023-017 · s3605.1, s3605.2
Not printed $11.4M 12/31/2026 31.8 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2025 RTEP p. 9
Mountain Substation “Convert Mountain 115 kV into a six-breaker ring bus”
115 kV
2025-10-08 TEAC
Informational Only - MetEd Local Plan Submission of the Supplemental Projects for 2025 p. 9
Mountain Substation “Convert Mountain 115 kV into a six-breaker ring bus”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.