Fort Bend County: substations in ERCOT transmission project tracking
23 substation names the workbook places in Fort Bend County.
| Substation | Projects | Utilities | kV | HIFLD record |
|---|---|---|---|---|
| Brazos Valley | 2 | CNP | 138 | Name and county agree |
| Crabb River Road | 1 | CNP | 138 | Name and county agree |
| DEWALT | 1 | CNP | 138 | Name and county agree |
| Flewellen | 8 | CNP | 138 | Name and county agree |
| Fort Bend | 3 | CNP | 138 | None |
| Foster | 1 | CNP | 138 | None |
| Fulshear | 2 | CNP | 138 | None |
| Missouri City | 2 | CNP | 138 | Name and county agree |
| Orchard | 1 | CNP | 138 | Name and county agree |
| Peters | 3 | CNP | 138 | None |
| Raider | 4 | CNP | 345 | None |
| Rosenberg | 1 | CNP | 138 | Name and county agree |
| Sienna | 2 | CNP | 138 | Name and county agree |
| Smithers | 2 | CNP | 345 | Name and county agree |
| Thompsons | 2 | CNP | 138 | Name and county agree |
| Twinwood | 3 | CNP | 138 | None |
| Twinwood (new) | 2 | CNP | 138 | None |
| WA Parish | 11 | CNP | 138, 345 | Name and county agree |
| WAP | 2 | CNP | 345 | None |
| WAParish | 4 | CNP | 345 | None |
| Waterhole | 1 | CNP | 345 | None |
| Whaley | 2 | CNP | 138, 345 | None |
| Wolf | 2 | CNP | 345 | None |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.