Peters
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Fort Bend County. First named in the release with data as of February 1, 2015.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand Peters 138kV Substation” — project 102542, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Fort Bend, TX: ERCOT queue, 10 active of 14. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Expand Peters 138kV Substation from ring bus to Breaker-and-Half configuration. Connect two circuits from Peters to TRENCH (TRE) customer owned substation ERCOT project 102542 |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Peters to TRENCK Fort Bend County |
Peters, TRENCK |
| Install (2) 14.4 MVAR distribution cap banks at Twinwood substation. Install (2) 14.4 MVAR distribution cap banks at Fulshear substation. Install (2) 40 MVAR transmission cap bank at Peters substation. Install (1) 40 MVAR transmission cap bank at Peters substation. (first of two) ERCOT project 99000B |
CNP Tier 4 |
Planned Future tab |
138 | May 2028 | Peters Fort Bend County |
Peters |
| Install (2) 14.4 MVAR distribution cap banks at Twinwood substation. Install (2) 14.4 MVAR distribution cap banks at Fulshear substation. Install (2) 40 MVAR transmission cap bank at Peters substation. Install (1) additional 40 MVAR switchable transmission cap bank at Peters substation. (second of two) ERCOT project 99000C |
CNP Tier 4 |
Planned Future tab |
138 | May 2029 | Peters Fort Bend County |
Peters |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 102542 | First listed | on the Future tab |
| October 1, 2025 | 99000B | First listed | on the Future tab |
| October 1, 2025 | 99000C | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.