WAP

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Fort Bend County. First named in the release with data as of June 1, 2018.

Fort Bendcounty as printed
345kV
CNPutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Fort Bend, TX: ERCOT queue, 10 active of 14. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade to increase thermal limits as part of FRM upgrades
Upgrade Bellaire to WAP Ckt.50A to increase thermal limits as part of FRM upgrades
ERCOT project 87479D
CNP
Tier 4
Conceptual
Current-year planned tab
345 Jul 2025 Bellaire to WAP
Harris / Fort Bend County
Bellaire, WAP
Upgrade to increase thermal limits as part of FRM upgrades
Upgrade Jeanetta to WA Parish Ckt.64A to increase thermal limits as part of FRM upgrades
ERCOT project 87479E
CNP
Tier 4
Conceptual
Current-year planned tab
345 Jul 2025 Jeanetta to WAP
Harris / Fort Bend County
Jeanetta, WAP

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202687479DStatus as reportedPlanned → Conceptual
July 13, 202687479EStatus as reportedPlanned → Conceptual
June 1, 202587479DMoved between tabsFuture → Current-year planned
June 1, 202587479EMoved between tabsFuture → Current-year planned
October 1, 202487479DFirst listedon the Future tab
October 1, 202487479EFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.