Substation Scout

Sidney

Named in 3 PJM planning documents for 2 projects, from July 8, 2025 to September 9, 2025.

Existingdescribed as
DAYTONzone
138kVkV as printed
3mentions

Also printed as: Sidney substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton Transmission Zone M-3 Process Auglaize County, Ohio
Dayton-2021-007 · S3376.1-.3
Conceptual $10.36M 12/31/2028 Not printed 2026-09-08*
SRRTEP Western
Dayton-2025-005 Conceptual $69.6M 6/2029 400 MW 2025-09-09
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named KETTLERSVILLE; MCCARTYVILLE → AMSTERDAM; FRANKLIN; MCCARTYVILLE; NEW KETTLERSVILLE; ROBERTS ROAD DELIVERY POINT; SIDNEY 2024-10-08 Not reported
Substations named SIDNEY → CREEKSIDE; MILLCREEK; SHELBY; SIDNEY 2025-07-08 2025-09-09

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
Dayton local plan submission of the supplemental projects for 2024 RTEP p. 9
Dayton Transmission Zone M-3 Process Auglaize County, Ohio No role wording
2025-09-09 TEAC
Item 07 - Dayton Supplemental Projects p. 8
Dayton-2025-005 “remote end work at Sidney”
138kV
2025-07-08 TEAC
Item 05 - Dayton Supplemental Projects p. 5
Dayton-2025-005 “vicinity of its Sidney substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.