Pioneer

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
ATSIzone
69/12 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AMPT Projects in ATSI Transmission Zone M3 Process Pioneer, OH
AMPT-2022-002
Not printed $12.6 M 5/31/2027 8 MW 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $26.5 M → $12.6 M Not reported Not reported
Cost estimate $12.6 M → $26.5 M 2024-10-08 Not reported
Cost estimate $26.5 M → $12.6 M 2024-10-08 2024-10-08
Substations named EAST FAYETTE; KEXON; KIDSTON; PIONEER; SNYDER; STRYKER → E FAYETTE; KEXON; PIONEER; SNYDER; STRYKER Not reported Not reported
Substations named E FAYETTE; KEXON; PIONEER; SNYDER; STRYKER → EAST FAYETTE; KEXON; KIDSTON; PIONEER; SNYDER; STRYKER 2024-10-08 Not reported
Substations named EAST FAYETTE; KEXON; KIDSTON; PIONEER; SNYDER; STRYKER → E FAYETTE; KEXON; PIONEER; SNYDER; STRYKER 2024-10-08 2024-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 38
AMPT Projects in ATSI Transmission Zone M3 Process Pioneer, OH “supplies the Pioneer 69/12 kV substation.”
69/12 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 38
AMPT Projects in ATSI Transmission Zone M3 Process Pioneer, OH No role wording
69/12 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.