Reynolds - Olive substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 4 with terminal status (shown grayed).
4 PJM queue filings name Reynolds - Olive as the point of interconnection, all in IN.
Target commercial operation dates as filed run from May 2021 to Dec 2026 (4 filings).
0active projects
0active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH2-419 | Reynolds - Olive 345 kV | 345 | 210 | Hybrid | Withdrawn | Dec 2026 |
| AI2-200 | Reynolds - Olive 345 kV | 345 | 144 | Solar | Withdrawn | May 2021 |
| AI2-197 | Reynolds - Olive 345 kV | 345 | 108 | Solar | Withdrawn | Dec 2021 |
| AI2-201 | Reynolds - Olive 345 kV | 345 | 108 | Solar | Withdrawn | May 2021 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in LaPorte County, IN
- Olive-University Park: 3 active, 205 MW of 6 filed
- University Park - Olive: none active of 2 filed
Other PJM queue substations in Starke County, IN
- Olive-Reynolds #2: 3 active, 336 MW of 7 filed
- Olive-Reynolds: 2 active, 264.3 MW of 6 filed
Other PJM queue substations in Pulaski County, IN
- Olive-Reynolds #2: 3 active, 336 MW of 7 filed
- Reynolds-Olive #1: 3 active, 334 MW of 3 filed
- Olive-Reynolds: 2 active, 264.3 MW of 6 filed
- Olive-Reynolds #1: 1 active, 180 MW of 3 filed
- Olive - Reynolds: 2 active, 110.7 MW of 5 filed
- Olive - Reynolds #2: 2 active, 96.2 MW of 2 filed
Site Scanner