Starke, IN interconnection queue

3 active projects totalling 366 MW in the PJM queue, plus 3 with terminal status (shown greyed).

3active projects
366active MW
6total filed
Queue IDProjectkVMWResourceStatus
AE2-240 Olive-Reynolds 1 & 2 345 kV 345 3,170 Not reported Withdrawn
AF1-215 Mammoth North Solar Project 345 180 Solar In Service
AI2-200 Reynolds - Olive 345 kV 345 144 Solar Withdrawn
AG2-245 Olive - Reynolds #1 345 kV 345 126 Solar Active
AI2-201 Reynolds - Olive 345 kV 345 108 Solar Withdrawn
AF2-134 Mammoth North Solar Project 345 60 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.