Olive - Reynolds #2 substation interconnection queue
2 active projects totalling 96.2 MW in the PJM queue.
2active projects
96.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-482 | Olive - Reynolds #2 345 kV | 345 | 78 | Battery | Active |
| C01-2035 | Olive - Reynolds #2 345 kV | 345 | 18.2 | Solar | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.