University Park - Olive substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name University Park - Olive as the point of interconnection, all in LaPorte County, IN.
Target commercial operation date as filed: Dec 2025 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH1-524 | University Park - Olive 345 kV | 345 | 70.2 | Solar | Withdrawn | Dec 2025 |
| AH1-525 | University Park - Olive 345 kV | 345 | 50 | Battery | Withdrawn | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in LaPorte County, IN
- Olive-University Park: 3 active, 205 MW of 6 filed
- Reynolds - Olive: none active of 4 filed