University Park - Olive substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name University Park - Olive as the point of interconnection, all in LaPorte County, IN.

Target commercial operation date as filed: Dec 2025 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH1-524 University Park - Olive 345 kV 345 70.2 Solar Withdrawn Dec 2025
AH1-525 University Park - Olive 345 kV 345 50 Battery Withdrawn Dec 2025

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.