Possum Point substation interconnection queue

8 active projects totalling 459 MW in the PJM queue, plus 10 with terminal status (shown greyed).

8active projects
459active MW
18total filed
Queue IDProjectkVMWResourceStatus
V1-031 Possum Point 230kV 230 875 Gas Withdrawn
P08 Possum Point n/r 600 Gas Withdrawn
AG2-306 Possum Point 230 kV 230 150 Battery Withdrawn
AH2-034 Possum Point 230kV 230 100 Battery Withdrawn
AH2-035 Possum Point 500kV 500 100 Battery Withdrawn
C01-1128 Possum Point 230 kV 230 100 Battery Active
AH1-696 Possum Point 230kV 230 94 Gas Active
AH2-032 Possum Point 115kV 115 60 Battery Withdrawn
AH2-033 Possum Point 115kV 115 60 Battery Withdrawn
C01-1127 Possum Point 115 kV 115 60 Battery Active
C01-1259 Possum Point 115 kV 115 60 Battery Active
R80 Possum Point Unit 6 230 60 Gas In Service
AH2-060 Possum Point 230 kV 230 55 Battery Withdrawn
C01-1264 Possum Point 230 kV 230 55 Battery Active
AH2-058 Possum Point 115 kV 115 30 Battery Withdrawn
C01-1263 Possum Point 115 kV 115 30 Battery Active
S99 Possum Point 230kV 230 20 Other Withdrawn
AA2-079 Possum Point Unit 6 230 0 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.