Possum Point Unit 6 (R80) is listed in the PJM interconnection queue as a 60 MW gas project in Prince William County, VA. The filing names Possum Point as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 26, 2017.

Queue IDR80
Project namePossum Point Unit 6
Status (as published)In Service
SubstationPossum Point
Point of interconnectionPossum Point 230kV
CountyPrince William
StateVA
Voltage230 kV
Capacity60 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2017-01-26
Source datasetserial

Same substation and county

Possum Point substation: 18 requests in the PJM queue, 8 active totaling 459 MW.

Queue IDProjectMWResourceStatus
C01-1128Possum Point 230 kV100BatteryActive
AH1-696Possum Point Unit 694GasEP
C01-1127Possum Point 115 kV60BatteryActive
C01-1259Possum Point 115 kV60BatteryActive
C01-1264Possum Point 230 kV55BatteryActive
C01-1263Possum Point 115 kV30BatteryActive
AA2-079Possum Point Unit 60GasIn Service
V1-031Possum Point 230kV875GasWithdrawn
P08Possum Point600GasWithdrawn
AG2-306Possum Point 230 kV150BatteryWithdrawn
AH2-034Possum Point 230kV100BatteryWithdrawn
AH2-035Possum Point 500kV100BatteryWithdrawn

5 more on the substation page.

Prince William, VA: 39 requests in the PJM queue, 14 active totaling 644 MW.

A substation with the same name is named in PJM transmission planning materials: Possum Point (DOM, 10 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity60
MFO640

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first