Old Church substation interconnection queue
4 active projects totalling 28.4 MW in the PJM queue, plus 4 with terminal status (shown greyed).
4active projects
28.4active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI2-113 | Old Church 230 kV | 230 | 100 | Battery | Withdrawn |
| AB1-027 | Mechanicsville Solar | 34.5 | 14 | Solar | In Service |
| AC2-162 | Sweetspire | 34.5 | 13.2 | Solar | Withdrawn |
| AC1-112 | Hollyfield Solar Facility | 34.5 | 10.9 | Solar | In Service |
| AC2-070 | Hollyfield II | 34.5 | 9.2 | Solar | Withdrawn |
| AE2-155 | Hanover Solar | 34.5 | 3.5 | Solar | In Service |
| AB1-059 | Old Church 34.5kV | 34.5 | 3.3 | Solar | Withdrawn |
| AG2-240 | Old Church 34.5 kV | 34.5 | 0 | Battery | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.