Old Church substation interconnection queue

4 active projects totalling 28.4 MW in the PJM queue, plus 4 with terminal status (shown greyed).

4active projects
28.4active MW
8total filed
Queue IDProjectkVMWResourceStatus
AI2-113 Old Church 230 kV 230 100 Battery Withdrawn
AB1-027 Mechanicsville Solar 34.5 14 Solar In Service
AC2-162 Sweetspire 34.5 13.2 Solar Withdrawn
AC1-112 Hollyfield Solar Facility 34.5 10.9 Solar In Service
AC2-070 Hollyfield II 34.5 9.2 Solar Withdrawn
AE2-155 Hanover Solar 34.5 3.5 Solar In Service
AB1-059 Old Church 34.5kV 34.5 3.3 Solar Withdrawn
AG2-240 Old Church 34.5 kV 34.5 0 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.