Hanover Solar
PJM queue ID AE2-155
Hanover Solar (AE2-155) is listed in the PJM interconnection queue as a 3.5 MW solar project in Hanover County, VA. The filing names Old Church as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2020.
| Queue ID | AE2-155 |
|---|---|
| Project name | Hanover Solar |
| Status (as published) | In Service |
| Substation | Old Church |
| Point of interconnection | Old Church 34.5 kV |
| County | Hanover |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 3.5 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2020-12-01 |
| Source dataset | serial |
Same substation and county
Old Church substation: 8 requests in the PJM queue, 3 active totaling 28.4 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AB1-027 | Mechanicsville Solar | 14 | Solar | In Service |
| AC1-112 | Hollyfield Solar Facility | 10.9 | Solar | In Service |
| AI2-113 | Old Church 230 kV | 100 | Battery | Withdrawn |
| AC2-162 | Sweetspire | 13.2 | Solar | Withdrawn |
| AC2-070 | Hollyfield II | 9.2 | Solar | Withdrawn |
| AB1-059 | Old Church 34.5kV | 3.3 | Solar | Withdrawn |
| AG2-240 | Old Church 34.5 kV | 0 | Battery | Withdrawn |
Hanover, VA: 30 requests in the PJM queue, 9 active totaling 930.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 5 |
| MW capacity | 3.5 |
| MFO | 25 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.