Jug Street substation interconnection queue

3 active projects totalling 400 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
400active MW
4total filed
Queue IDProjectkVMWResourceStatus
C01-2017 Jug Street 138 kV 138 200 Battery Active
AI2-226 Jug Street 138 kV 138 120 Battery Withdrawn
C01-1461 Jug Street 138 kV 138 120 Battery Active
AF1-062 Flint Grid 138 80 Battery Engineering and Procurement

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.