Hoytdale substation interconnection queue

1 active project totalling 150 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
150active MW
2total filed
Queue IDProjectkVMWResourceStatus
AG2-621 Hoytdale 138 kV 138 150 Battery Active
AB1-147 Hoytdale 138kV 138 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.