Beaver, PA interconnection queue

13 active projects totalling 5,701.7 MW in the PJM queue, plus 14 with terminal status (shown greyed).

13active projects
5,701.7active MW
27total filed
Queue IDProjectkVMWResourceStatus
R67 Beaver Valley 345kV 345 2,510 Coal Withdrawn
C01-1243 Bruce Mansfield 345 kV 345 2,500 Gas Active
AH1-674 Not reported n/r 1,650 Gas Withdrawn
N13 Beaver Valley n/r 1,630 Nuclear In Service
C01-1956 Hoytdale - Bruce Mansfield 345 kV 345 931.1 Gas Active
C01-2207 Hoytdale - McClelland 345 kV & Hoytdale - Bruce Mansfield 345 kV 345 500 Gas Withdrawn
C01-1865 Sammis - Beaver Valley 345 kV 345 250 Hybrid Withdrawn
C01-1919 Sammis - Beaver Valley 345 kV 345 250 Hybrid Withdrawn
AG2-621 Hoytdale 138 kV 138 150 Battery Active
Y2-065 Valley-Raccoon 138kV 138 97 Gas Withdrawn
Y3-103 Pennsylvania Chemicals Generating Facility 138 97 Gas In Service
O53 Beaver Valley 1 n/r 81 Nuclear In Service
O54 Beaver Valley 2 n/r 77 Nuclear In Service
C01-1503 Beaver Valley 345 kV 345 70 Nuclear Active
C01-1504 Beaver Valley 345 kV 345 70 Nuclear Active
AH2-253 Beaver Valley - Crescent 138 kV 138 65 Hybrid Withdrawn
U3-030 Beaver Valley Power Station n/r 38 Nuclear In Service
U3-029 Beaver Valley Power Station n/r 37 Nuclear In Service
U1-080 Montgomery Lock & Dam n/r 35 Hydro Withdrawn
AG1-292 Midland 138 kV 138 21.5 Hydro Withdrawn
AG2-233 Montgomery Hydroelectric 23 kV 23 17.5 Hydro Withdrawn
AH2-063 North Ramsey 23 kV 23 12 Solar Withdrawn
AE2-114 BE-PINE 1 Cain Road 23 10.3 Solar In Service
AE2-115 BE-PINE 2 Dam Road 23 10.3 Solar In Service
AH2-064 South Ramsey 23 kV 23 6 Solar Withdrawn
AG1-330 ASD Brick Plant PA2 Solar 12.5 4.5 Hybrid Withdrawn
AB1-147 Hoytdale 138kV 138 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.