Substation Scout

Corwin - Elk substation interconnection queue

2 active projects totalling 108 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
108active MW
3total filed
Queue IDProjectkVMWResourceStatus
AI1-074 Corwin - Elk 138 kV 138 96 Hybrid Withdrawn
AG2-548 Corwin - Elk 138 kV 138 54 Hybrid Active
AG2-665 Corwin - Elk 138 kV 138 54 Hybrid Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.