Corwin - Elk substation interconnection queue

2 active projects totaling 108 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Corwin - Elk as the point of interconnection, all in OH.

Target commercial operation dates as filed run from Dec 2027 to Oct 2028 (3 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (2 filings).

2active projects
108active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI1-074 Corwin - Elk 138 kV 138 96 Hybrid Withdrawn Dec 2027
AG2-548 Corwin - Elk 138 kV 138 54 Hybrid Active Oct 2028
AG2-665 Corwin - Elk 138 kV 138 54 Hybrid Active Oct 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Jackson County, OH

All 10 PJM queue filings in Jackson County, OH.

Other PJM queue substations in Vinton County, OH

All 8 PJM queue filings in Vinton County, OH.