Corwin - Elk 138 kV
PJM queue ID AG2-548
Corwin - Elk 138 kV (AG2-548) is listed in the PJM interconnection queue as a 54 MW hybrid project in Vinton County, OH. The filing names Corwin - Elk as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of October 31, 2028.
| Queue ID | AG2-548 |
|---|---|
| Project name | Corwin - Elk 138 kV |
| Status (as published) | Active |
| Substation | Corwin - Elk |
| Point of interconnection | Corwin - Elk 138 kV |
| County | Vinton |
| State | OH |
| Voltage | 138 kV |
| Capacity | 54 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2028-10-31 |
| Source dataset | cycle |
Same substation and county
Corwin - Elk substation: 3 requests in the PJM queue, 2 active totaling 108 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-665 | Corwin - Elk 138 kV | 54 | Hybrid | Active |
| AI1-074 | Corwin - Elk 138 kV | 96 | Hybrid | Withdrawn |
Vinton, OH: 8 requests in the PJM queue, 6 active totaling 334.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Hamden Energy LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 80.0 |
| MW capacity | 54.0 |
| MFO | 80.0 |
| Submitted date | 3/31/2021 |
| Last updated | 9/1/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.