Flatlick substation interconnection queue
1 active project totalling 89.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).
1active projects
89.6active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-2045 | Flatlick 765 kV | 765 | 624.5 | Gas | Withdrawn |
| X3-051 | Flatlick 765kV | 765 | 610 | Gas | Withdrawn |
| AF2-395 | Rolling Hills Generating | 765 | 89.6 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.