Cole substation interconnection queue
2 active projects totaling 144 MW in the PJM queue, plus 1 with terminal status (shown grayed).
3 PJM queue filings name Cole as the point of interconnection, all in Franklin County, OH.
Target commercial operation dates as filed run from Dec 2025 to Dec 2027 (3 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: AEP (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-214 | Pleasant Prairie Solar Energy Center | 345 | 120 | Solar | Partially in Service - Under Construction | Dec 2027 |
| AH1-318 | Cole 345 kV | 345 | 60 | Battery | Withdrawn | Dec 2025 |
| AF1-275 | Pleasant Prairie Solar Energy Center | 345 | 24 | Solar | Partially in Service - Under Construction | Dec 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Cole (AEP, 5 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-11-02 | AE2-214 | Status change | n/a | Under Construction → Partially in Service - Under Construction |
| 2026-11-02 | AF1-275 | Status change | n/a | Under Construction → Partially in Service - Under Construction |
Same name on other Substation Scout pages
Other sources that print a substation named “Cole” in OH. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Cole: Expansion Tracker, PJM planning: PJM system-wide state not printed
Other PJM queue substations in Franklin County, OH
- Cole Road: 1 active, 40 MW of 2 filed
- Apple Grove: 1 active, 27 MW of 3 filed
- City of Columbus: 1 active, 7 MW of 3 filed
- Hayden: none active of 3 filed
- Bixby: none active of 2 filed