Clinch River substation interconnection queue
5 active projects totaling 630 MW in the PJM queue.
5 PJM queue filings name Clinch River as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Mar 2012 to May 2026 (5 filings).
Transmission owner as filed: AEP (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| Q43 | Virginia City Hybrid Energy Center - 1 Unit | 138 | 534 | Coal | In Service | Mar 2012 |
| S100 | Virginia City Hybrid Energy Center | 138 | 80 | Coal | In Service | Mar 2012 |
| Y2-067 | Virginia City Hybrid Energy Center | 138 | 12 | Coal | In Service | Nov 2012 |
| C01-1284 | Clinch River 138 kV | 138 | 2 | Gas | Active | May 2026 |
| C01-1285 | Clinch River 138 kV | 138 | 2 | Gas | Active | May 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Clinch River (AEP, 2 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Wise County, VA
No other substation in Wise County, VA is named as a point of interconnection in the PJM queue.
Other PJM queue substations in Russell County, VA
No other substation in Russell County, VA is named as a point of interconnection in the PJM queue.