Russell, VA interconnection queue

4 active projects totalling 44 MW in the PJM queue, plus 1 with terminal status (shown greyed).

4active projects
44active MW
5total filed
Queue IDProjectkVMWResourceStatus
AG2-168 Clinch River-Copper Ridge 138 kV 138 63.3 Solar Withdrawn
Y3-039 Clinch River Power Plant n/r 20 Gas In Service
Y3-040 Clinch River Power Plant n/r 20 Gas In Service
C01-1284 Clinch River 138 kV 138 2 Gas Active
C01-1285 Clinch River 138 kV 138 2 Gas Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.