Baker substation interconnection queue

5 active projects totalling 1,541.8 MW in the PJM queue, plus 3 with terminal status (shown greyed).

5active projects
1,541.8active MW
8total filed
Queue IDProjectkVMWResourceStatus
C01-1325 Baker 345 kV 345 1,046 Gas Active
W1-035 Baker 345kV 345 750 Gas Withdrawn
C01-1131 Baker 345 kV 345 458 Gas Active
W3-162 Riverside Generating Stations 345 20 Gas In Service
AB1-149 Baker 138kV 138 15.8 Wind Withdrawn
AD1-125 Short Mountain Wind Energy 138 11.8 Wind Engineering and Procurement
Y2-045 Riverside Generating Station 345 6 Gas In Service
X2-006 Riverside Generating Station 345 0 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.