Remington BESS

PJM queue ID AG1-152

Remington BESS (AG1-152) is listed in the PJM interconnection queue as a 40 MW battery project in Fauquier County, VA. The filing names Remington CT as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of September 1, 2029.

Queue IDAG1-152
Project nameRemington BESS
Status (as published)Engineering and Procurement
SubstationRemington CT
Point of interconnectionRemington CT 230 kV
CountyFauquier
StateVA
Voltage230 kV
Capacity40 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-09-01
Source datasetserial

Same substation and county

Remington CT substation: 10 requests in the PJM queue, 6 active totaling 186.7 MW.

Queue IDProjectMWResourceStatus
AH1-220Remington BESS60BatteryEP
AH1-685Remington GT226GasEP
AH1-684Remington GT123GasEP
AH1-693Remington GT420GasEP
AE2-132Remington GT317.7GasIn Service
W1-074Remington CT 230kV498GasWithdrawn
AI2-287Remington CT 230 kV18.3GasWithdrawn
AI2-288Remington CT 230 kV16.9GasWithdrawn
AI2-289Remington CT 230 kV16.3GasWithdrawn

Fauquier, VA: 52 requests in the PJM queue, 18 active totaling 2,367 MW.

A substation with the same name is named in PJM transmission planning materials: Remington CT (DOM, 8 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy100
MW capacity40
MFO100

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.