Woods Landing Energy Storage

PJM queue ID AF2-413

Woods Landing Energy Storage (AF2-413) is listed in the PJM interconnection queue as a 250 MW battery project in Atlantic County, NJ. The filing names Raritan River as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of January 31, 2031.

Queue IDAF2-413
Project nameWoods Landing Energy Storage
Status (as published)Engineering and Procurement
SubstationRaritan River
Point of interconnectionRaritan River 115 kV
CountyAtlantic
StateNJ
Voltage115 kV
Capacity250 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2031-01-31
Source datasetserial

Same substation and county

Raritan River substation: 8 requests in the PJM queue, 4 active totaling 1,060 MW.

Queue IDProjectMWResourceStatus
W4-009Woodbridge Energy Center725GasIn Service
C01-1698Raritan River 230 kV85BatteryActive
X4-005Raritan River 230kV0GasIn Service
Y1-025Raritan River 230kV725GasWithdrawn
AG2-076Raritan River 230 kV660Not reportedWithdrawn
AD1-113Woodbridge Energy Center75GasWithdrawn
C01-1012Raritan River 230 kV0BatteryWithdrawn

Atlantic, NJ: 93 requests in the PJM queue, 12 active totaling 301.6 MW.

A substation with the same name is named in PJM transmission planning materials: Raritan River Substation (JCPL, 21 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy250
MW capacity250
MFO250

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.