Timber Road IV Wind Farm (Southern Phase)

PJM queue ID AC1-173

Timber Road IV Wind Farm (Southern Phase) (AC1-173) is listed in the PJM interconnection queue as a 9.9 MW wind project in Paulding County, OH. The filing names Logtown as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 31, 2020.

Queue IDAC1-173
Project nameTimber Road IV Wind Farm (Southern Phase)
Status (as published)In Service
SubstationLogtown
Point of interconnectionLogtown 138kV
CountyPaulding
StateOH
Voltage138 kV
Capacity9.9 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2020-03-31
Source datasetserial

Same substation and county

Logtown substation: 4 requests in the PJM queue, 3 active totaling 59.8 MW.

Queue IDProjectMWResourceStatus
AG1-369Timber Road Solar Park III29.9SolarEngineering and Procurement
AF2-377Timber Road Storage III20BatteryEngineering and Procurement
AI2-092Logtown 138 kV40.3WindWithdrawn

Paulding, OH: 28 requests in the PJM queue, 12 active totaling 250.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy75.9
MW capacity9.9
MFO75.9

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first