Samson Solar 2
ERCOT queue ID 21INR0490
Samson Solar 2 (21INR0490) is listed in the ERCOT interconnection queue as a 203 MW solar project in Lamar County, TX. The filing names TTRSW as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2026. It records the screening study as complete on January 4, 2019, the full interconnection study as approved on June 9, 2020 and the interconnection agreement as signed on August 27, 2020.
| Queue ID | 21INR0490 |
|---|---|
| Project name | Samson Solar 2 |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | TTRSW |
| Point of interconnection | 345 kV TTRSW 11688 |
| County | Lamar |
| State | TX |
| Voltage | 345 kV |
| Capacity | 203 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
TTRSW substation: 2 requests in the ERCOT queue, 2 active totaling 520.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 22INR0203 | Delilah Solar 2 | 317.6 | Solar | SS Completed, FIS Completed, IA |
Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Samson Solar Energy II LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2020-08-27 |
| Screening study complete | 2019-01-04 |
| Full interconnection study approved | 2020-06-09 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.