Maleza Solar II (23INR0227) is listed in the ERCOT interconnection queue as a 254.9 MW solar project in Wharton County, TX. The filing names tap Blue – Hillje Ckt.#27 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on June 24, 2021.

Queue ID23INR0227
Project nameMaleza Solar II
Status (as published)SS Completed, FIS Started, No IA
Substationtap Blue – Hillje Ckt.#27
Point of interconnectiontap Blue – Hillje 345 kv Ckt.#27
CountyWharton
StateTX
Voltage345 kV
Capacity254.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

tap Blue – Hillje Ckt.#27 substation: 3 requests in the ERCOT queue, 3 active totaling 660.6 MW.

Queue IDProjectMWResourceStatus
21INR0220Maleza Solar254.9SolarSS Completed, FIS Not Started, IA
21INR0456Maleza Storage150.8BatterySS Completed, FIS Started, No IA

Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBrush Solar, LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Screening study complete2021-06-24
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.