Tap 345-kV Austrop to Zorn substation interconnection queue
2 active projects totalling 306.2 MW in the ERCOT queue.
2active projects
306.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25INR0422 | Waterloo Solar 1 | n/r | 200.6 | Solar | SS Completed, FIS Started, IA |
| 25INR0447 | Waterloo BESS 1 | n/r | 105.6 | Battery | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.