(#) LOST PINES substation interconnection queue

3 active projects totaling 1,106 MW in the ERCOT queue.

3 ERCOT queue filings name (#) LOST PINES as the point of interconnection, all in Bastrop County, TX.

Target commercial operation date as filed: Jun 2033 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: LCRA (3 filings).

3active projects
1,106active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
30INR0052 Lost Pines Power Park 345 880 Gas SS Completed, FIS Started, IA Jun 2033
29INR0166 LOST PINES GAS RECIP 345 113 Gas SS Completed, FIS Started, IA Jun 2033
31INR0010 LOST PINES GAS RECIP PHASE 2 345 113 Gas SS Completed, FIS Started, IA Jun 2033

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Bastrop County, TX

All 16 ERCOT queue filings in Bastrop County, TX.