Stainback Switch (bus #) - Elrod Switch (bus #) substation interconnection queue

3 active projects totaling 431.7 MW in the ERCOT queue.

3 ERCOT queue filings name Stainback Switch (bus #) - Elrod Switch (bus #) as the point of interconnection, all in Ellis County, TX.

Target commercial operation date as filed: Oct 2028 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Galaxy Solar, LLC (3 filings).

3active projects
431.7active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
27INR0219 Galaxy Solar n/r 177.3 Solar SS Completed, FIS Started, No IA Oct 2028
27INR0220 Galaxy Storage n/r 155 Battery SS Completed, FIS Started, No IA Oct 2028
28INR0355 Galaxy I Solar n/r 99.4 Solar SS Completed, FIS Started, No IA Oct 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Ellis County, TX

All 30 ERCOT queue filings in Ellis County, TX.